Where simulation pays off

Examples from production and logistics.

Every system is different. The questions are often similar. Here are six of them, and what a simulation model shows. The illustrations are schematic; no customer data.

Schematic of batch production: raw parts, machine A with a batch of four, a buffer partly filled, machine B with changeover, an inspection that sends good parts on and scrap into a red bin.

Production

Batches, buffers and scrap

Which batch size, and how big a buffer? Single parts are machined in batches on several machines, with changeovers, buffers in between and scrap after inspection. The model shows how batch size, buffer capacity and scrap together decide output and lead time, and where a larger buffer stops paying off.

Schematic of large component assembly: sub-assemblies on the left feed three assembly docks, each with a large frame and a progress bar; assembly teams work on two docks and one team is on the way.

Production

Large components and assembly

How many assembly docks, and how many teams? Large components stay on their dock for hours or days while sub-assemblies arrive and teams move between docks. The simulation shows where components wait for parts or people, and which combination of docks, teams and shift model meets the delivery dates.

Schematic of a takted line with six stations; bars above show the work content of each station against the takt line, and station four exceeds the takt.

Production

Takted line

Does the line really hold the takt? On paper every station fits into the takt. With variability, failures and missing parts the picture changes. The model shows how often the line misses the takt, which station causes it, and whether buffers, rebalancing or a floater help most.

Top view of a hall with three assembly lines below one overhead crane; one job on line one and one on line three wait for the crane.

Logistics

A crane as the bottleneck

One crane for all lines, or one per line? Several assembly lines share an overhead crane, and jobs wait whenever it is busy elsewhere. The simulation compares shared and dedicated cranes, staggered line starts and crane failures, so you see what each option costs in late units and waiting time. Example study below →

Top view of a hall with automated guided vehicles on a loop between stations; next to it a curve of waiting time for transport over the number of vehicles that flattens out, with the sufficient fleet size marked.

Logistics

How many AGVs?

How many vehicles are enough? Automated guided vehicles serve the stations of a hall on fixed routes. Too few, and production waits for material; too many, and they block each other. The simulation runs the hall with different fleet sizes and shows the point where one more vehicle no longer helps.

Site plan with five halls, a warehouse and a gate connected by roads; tugger trains and trucks are on the way and one crossing is marked as a hot spot.

Intralogistics

Transports on the site

Which vehicles, how many, and which routes? Material moves between halls, warehouse and gate by tugger train, forklift or truck. The model brings routes, crossings, loading times and shift calendars together and shows whether the fleet keeps production supplied, and where traffic piles up.

Example study · A crane as the bottleneck

Same output, very different robustness.

Three assembly lines for a large component, a takt of three working days, staggered by a third of the takt; every transport by crane. Over 20 simulated years per variant, every variant builds the same 87 units per line and year, so an average-based calculation calls both concepts equal. The difference is robustness.

Two bar charts of the crane study for crane availabilities from no failures to 97 percent, with three bars each: units more than one shift late rise to 6 percent with one crane per line, to 13 percent with one crane for three lines serving assembly lifts first, and to 20 percent with one crane for three lines; the delay of the worst 5 percent of units rises to 10, 18 and 24 hours.
Synthetic example model, 20 simulated years per variant, simulated with 3LYNX.CORE.
Units more than one shift late, by crane concept and crane availability
Crane availabilityOne crane per lineOne crane for three lines, assembly lifts firstOne crane for three lines
99 %2.0 %4.0 %6.7 %
98 %3.5 %7.2 %10.4 %
97 %5.9 %13.0 %19.5 %

With one crane for three lines, up to 57 % of the units are more than one shift late in a bad year. Even without any failure, the shared crane makes the stations wait 3.8 % of their time, because lifts of different lines collide despite the offset. A shared crane with 99 % availability is about as robust as three dedicated cranes with 97 %.

Serving assembly lifts before unloading cuts the late units of the shared crane by about a third (units more than one shift late at 99 / 98 / 97 %: 4.0 / 7.2 / 13.0 % instead of 6.7 / 10.4 / 19.5 %) – still about twice as many as with one crane per line (2.0 / 3.5 / 5.9 %).

Your question is not on the list?

Most are, in one form or another. Talk to us.